Rubber Install – Day 2

15 additional teepads were poured today, and they look amazing.  We haven’t confirmed yet with the rubber company, but it looks like all but one of the Phase 1 teepads has been completed (16-Long).  Next up is finishing the site work around the teepads to ensure proper drainage and soil retention.  The tee areas will be graded and seeded.  Please try not to step on the seed while playing the course until the grass takes (to the extent you can).

We will post on here as soon as we have confirmation that the new holes are playable.  In the meantime, keep off the rubber teepads that were just poured.