Back to work

The 28 phase 1 teepads are in final stages of preparation for rubber.  They have been filled with gravel and timber retaining walls will be constructed as needed this week.  Next week, the gravel will get compacted and the rubber will be poured.  Please stay off the pads if you notice the gravel has been compacted, as that is the important finishing part.

Photos from today:

On another note, the course needs some TLC due to the abundant rain this year.  If you want to help beat back the vegetation, please contact us.  We’re working with Park Pride to arrange a massive volunteer day on 9/20/2013 with 50 to 100 volunteers, after which the course will be looking MUCH better.