The course is fully marked for construction, which is scheduled to begin one week from today on July 8, 2013.  Construction during this phase will include 28 of the 35 teepads and should last 2-3 weeks, depending on weather.  Please play around the under construction areas if you use the course during this time.

For this week, all of the teepads have been marked with red/blue wood stakes.  Be mindful of these and be careful not to disturb them.  We’ve also marked many of the new pin positions using orange flagging and painted wood stakes.  The course will improve dramatically in the coming month as the final pin positions are installed and the teepads are built.

We are have a high need for volunteer labor during the next month.  If you have any interest in being part of the construction process, contact us through the website form.